Logodogs01
box01dogs02
Customer ServiceInside ChugachEnergy InfoNews & EventsfillblankPay your BillContact Us
fillblank

News

Announcements

Publications
Request

Links

Projects

Cooper Lake Hydroelectric Project Home



Adobe® Acrobat® ReaderTM is required to view PDF files. You can download a free copy by clicking on the button below.



News and Events

Projects


Land-use actions for projects

Chugach has several land-use actions underway or pending to enable future projects – or in one case, to remedy an adverse result of a prior project. Chugach has been discussing the following projects with neighborhood councils, municipal officials and others.


Chugach is seeking to rezone its 44-acre headquarters complex from I-1 to I-2 in advance of construction of the Southcentral Power Project. Chugach has operated a gas-fired power plant on the site since 1964, but if the Assembly approves proposed changes to Title 21 the I-2 zoning would be preferred. The Planning & Zoning Commission approved the change on April 5. It will also go before the Assembly.

Click here for more details




The Southcentral Power Project will be built on land Chugach is currently using for activities, which will be moved to a recently purchased parcel of land between the headquarters parcel and Minnesota Drive. One of the things that will need to move is the helipad where crews needing to patrol or access remote parts of the system are picked up and dropped off by Chugach's contracted helicopter service. This summer Chugach will be submitting a conditional use permit application for the proposed new helipad site.

Meeting Schedule:

May 5, 2010Spenard Community Council
May 6, 2010Turnagain Community Council
May 10, 2010Sand Lake Community Council
May 13, 2010Taku-Campbell Community Council





Since the 1990s, Chugach has owned four vacant lots adjacent to the Girdwood Substation. This summer Chugach will seek a conditional use permit for three of the unused lots to accommodate improvements to the substation, including the installation of new switchgear.

Click here for more details



Abbott Area Substation

Chugach has made an offer to purchase a 2-acre lot for a new substation, provided it can secure conditional use of the property for that purpose. The land is on the south side of O'Malley Road east of Lake Otis Parkway. An application for a conditional use permit is expected to be submitted this summer.

Chugach's offer to purchase the property along O'Malley Road for a substation site is conditional. These conditions include passing an environmental screening, being found to be geotechnically appropriate for the intended use, and Chugach securing a conditional use permit to use the property as the location for a substation. Under the terms of the purchase agreement, Chugach has 6 months to complete all necessary actions or the sale can be cancelled.

Meeting Schedule:

April 15, 2010Huffman/O'Malley Community Council
April 29, 2010Abbott Loop Community Council
July 15, 2010Huffman/O'Malley Community Council
August 2, 2010Planning & Zoning Commission
September 13, 2010Planning & Zoning Commission





Chugach is still working with the Municipality of Anchorage on a solution for land lost at the Dowling Substation to a recent road project. Chugach is seeking an equal amount of land to enable future improvements to be made at the substation, located near the intersection of Dowling and Elmore roads.



Girdwood Substation Upgrade

Chugach operates a substation on lots 17 and 18, Block 3, Girdwood Original Townsite. This substation has been in operation since the early 1970s. Plans for an expansion of this station in the 1990s led to the purchase of Lots 19 to 22 adjacent to, and north of the existing station. The upgrade plans were postponed, when the availability of natural gas slowed the growth of demand for electric energy in the community.

Condition and age of equipment installed in the station now make it necessary to replace the low voltage (25kV) open-air switchgear as well as the control enclosure. In order to accommodate future load growth and increase service reliability, Chugach plans to install 25kV switchgear in a metal enclosure, which will provide capacity for 2 transformers, 3 feeders and a bus tie. It will also include the controls for the high voltage (115kV) switchgear and other auxiliary equipment, such as batteries, chargers and low voltage power panels. Locating the new enclosure on the site made it necessary to determine future development of the high voltage (115kV) connections.

Load forecasts indicate that a second transformer will need to be installed between 2020 and 2025. At that time, the existing high voltage switching arrangement will not be adequate to maintain reliable service. It will be upgraded to allow termination of a looped 115kV circuit with a circuit breaker to separate line sections and taps to 2 transformers. This will occupy most of 5 (Lots 17 to 21) of the 6 lots. In preparation for this expansion, Chugach will clear and fence the area needed for the final build out at the time the 25kV switchgear is installed. A wooden fence and planting of shrubs on the exposed sides of the station will enhance the appearance.

The present zoning of the additional area required for the full build out of the substation is gC-3, which allows the substation upgrade under a conditional use permit issued by the Municipality of Anchorage.

In 2009 Chugach evaluated alternative sites for a substation. In early 2010 Chugach presented the results of that study to the Girdwood Board of Supervisors. Chugach is seeking a Conditional Use Permit for the project on land it owns adjacent to the existing substation.

Schedule
Submit Conditional Use Permit ApplicationJuly/August 2010
Receive Conditional Use PermitOctober 2010
Procure Equipment2011
Construct Upgrade2012/13

Southcentral Power Project

New, efficient combined-cycle plant

Chugach has determined its least cost resource plan is to build new, more-efficient generation to replace its existing less efficient, aging generation. The Municipality of Anchorage d/b/a Municipal Light & Power (ML&P) also desires new, more-efficient generation. When compared with the costs to design, construct and operate smaller, separate plants, economies-of-scale can be achieved through the joint construction and operation of a larger, single plant capable of producing the new generation collectively required. Therefore, Chugach and ML&P plan to jointly build and own approximately 180 to 270 megawatts of new more efficient, combined-cycle generation. The new plant (the Southcentral Power Project, or "SPP"), the "Project", would be located adjacent to Chugach's existing International Station at 5601 Electron Drive in Anchorage, Alaska.

  • Schedule
  • Meetings/News
  • Reports
  • Contact Information
  • Maps, Pictures & Drawings
  • Bid Opportunities





  • Projects in the Distribution Facilities Undergrounding Plan 2011 - 2015

    On March 1, 2005, the Anchorage Assembly adopted certain revisions to Section 21.90, Utility Distribution Facilities, of the Anchorage Municipal Code. These revisions required an electric utility to "include as part of its annual capital improvement plan, a five-year undergrounding program". In each of the years of this program the electric utility shall plan on expending "at least two percent of a three-year average of its annual gross retail revenues derived from utility service connections within the municipality". This requirement means that Chugach Electric Association (Chugach) is required to spend approximately $3.2 million annually to underground existing overhead facilities. Over expenditures or under expenditures may be carried over as an adjustment to the following year's obligation.

    In the development of the five-year undergrounding program the electric utility is allowed to choose which existing lines to underground. Specifically, priorities for the program "shall be based on undergrounding in conjunction with the utility's essential system improvements and then by target areas".

    The following document contains Chugach's five-year undergrounding program. Overall, the plan calls for $15,569,365 to be expended on undergrounding existing overhead lines from 2011 to 2015, for an average of $3,113,373 annually.

    The projects were chosen taking into account Chugach's overall system needs and consideration of the designated target areas. The inclusion of a project within this plan does not guarantee that the project will be constructed in the designated year.

  • Project Identification

  • Project Selection

  • List of Projects


  • Complete Distribution Facilities Undergrounding Plan 2011-2015 (PDF, 12MB)





    Projects in the 5-year Capital Improvement Plan 2008-2012

    South Anchorage Loop

    The South Anchorage Loop refers to a series of projects Chugach undertook to strengthen the regional transmission system and provide more reliable power for South Anchorage. The overall scope of the project entailed construction of a new transmission substation in South Anchorage (Retherford), and completion of transmission line segments to link it with Chugach's two existing transmission substations (International and University).

    University Substation to Retherford Substation 138-kV line

    A 138kV transmission line will be constructed to link the Retherford Substation south of Dimond Center with the University Substation south of Tudor between Elmore and Boniface. The line will be routed along O'Malley Road between the Alaska Railroad and Elmore Road to connect with an existing 138-kV line that runs north and south along the Elmore alignment.

    Questions or comments on this project may be sent to:

    Jon Sinclair, PE
    Senior Project Engineer
    jon_sinclair@chugachelectric.com

    Abbott Area Substation
    Chugach plans to build a new distribution substation at a site to be determined to serve the growing electrical needs of customers in this area of southeast Anchorage. This project is scheduled for 2010.




    Cooper Lake Hydroelectric Project Home



    Hope Line Relocation Study



    New Generation




    Customer Service | Inside Chugach | Energy Info | News & Events | Pay your Bill | Contact Us | Site Map
    Copyright © 2010 Chugach Electric Association, Inc. All Rights Reserved.
    box03